The certification progress for stages 3 & 4 is progressing well, we estimate titles for both stages will be issued around mid-September.

Stage 5 construction is now expected to recommence in a couple of weeks, as a new truck access point further from existing homes is currently organised. Titles are still expected in Feb/March 2019. Stage 6 construction is still planned to commence in September.

We are also still in the process of reconfiguring The Green’s final stages before a final land release. We hope to have further information to potential buyers as soon as possible. If you or anyone you know is interested in large allotments of at least 2000sqm, contact The Green on 1300 THE GREEN to receive pre-release updates.