June/July Update

The Green WinchelseaConstruction Updates

Stages 3 & 4 construction is now complete with street tree planting currently scheduled to commence next week. Stage 2 trees will also be planted. The certification progress for stages 3 & 4 is progressing well. We will be in contact with purchasers should it look like titles will be earlier than expected. We will get a better idea in the next few weeks.

Stage 5 construction is expected to recommence on site by the end of the month with titles still expected in February 2019. Stage 6 construction is currently planned to commence in September.

We are still in the process of reconfiguring The Green’s final stages before a final land release. We hope to have further information to potential buyers in the next month. However, if you or anyone you know is interested in large allotments of at least 2000sqm, contact The Green on 1300 THE GREEN to receive pre-release updates.