With all lots in Stages 1 to 6 now sold, residents enjoying their homes in Stage 1, housing construction flying in Stage 2 with some near completion; The Green is quickly changing from a subdivision to a vibrant community.

Stages 3 & 4 construction are still on track for works completion in June/July with titles issued in September/October, subject to no unforeseen hold ups. Stage 5 construction is due to commence in late June with Stage 6 to commence shortly after. Titles for Stage 5 are now expected February 2019 with Stage 6 to follow soon after, again subject to no unforeseen hold ups.

We are currently reconfiguring The Green’s future stages before a final land release. We hope to have further information to potential buyers in the next month or two. However, if you or anyone you know is interested in larger allotments of at least 2000sqm, contact The Green on 1300 THE GREEN to receive pre-release updates.